Request fuel and follow purchase orders

A purchase request states a fuel need for a tank, and a manager approves it. A purchase order follows what you ordered from a supplier and what has already arrived. Neither one adds fuel to the tank: only a recorded delivery does.

Reviewed 14 October 2026

Who this is for

Requests and purchase orders: inventory manager, station manager, regional manager or owner. Approving requests: station manager, regional manager or owner. The accountant can view purchase orders.

Before you begin

Check the tank level in “Stock” and the requests already in progress, so you do not order twice.

1Create and submit a purchase request

  1. Open the “Purchase Requests” tab of the Stock page, or More → “Purchase Requests”. Click “New request”.
  2. Choose the station, the tank and the “Volume (L)”. The estimated unit cost, the supplier and the notes are optional.
  3. Click “Create & submit”. To finish later, choose “Save as draft”, then “Submit” in the list.
  4. Follow the status: “Draft”, “Submitted”, “Confirmed” or “Rejected”.
What you should see

The submitted request waits for a manager’s decision. Only the person who created a draft can submit it.

2Approve or reject a request

  1. Open “Purchase Requests”. The list shows “Submitted” requests first.
  2. Check the tank, the volume and the supplier.
  3. Click “Confirm”, or “Reject” and give the “Rejection reason”.
  4. You cannot decide your own request if another manager of the station can do it.
What you should see

A confirmed request shows “Delivery pending”. If a supplier was chosen, a purchase order is created automatically: open it with “View purchase order”.

3Use reorder suggestions

  1. Open More → “Reorder Suggestions”. Filter by station if needed.
  2. Read the suggested quantity, the estimated cost and the proposed supplier.
  3. Click “Create draft request” to take it up, or “Dismiss”.
What you should see

The suggestion becomes a draft request. Check it, then submit it: it follows the same approval path.

4Create and follow a purchase order

  1. Open More → “Purchase Orders”, then click “Create purchase order”.
  2. Choose the station and the supplier. For each line, enter the “Receiving tank”, the “Quantity (litres)” and the “Unit price (FCFA/L)”.
  3. Add the expected delivery, taxes and notes if needed, then click “Save draft”.
  4. On the order, click “Download PDF” to send it to the supplier yourself. Then click “Record as sent”: FuelOps does not send any email.
  5. When the supplier accepts, click “Confirm supplier acceptance”. Once everything is received, click “Close order”.
What you should see

The order status shows where the order stands. Fuel received is recorded on the order, line by line: see the deliveries chapter.

A practical example

You order 10,000 L of diesel. The first truck brings 6,000 L: record 6,000 L on the line. The order shows “Received: 6,000 / 10,000 L” and what is still to receive. Record the remaining 4,000 L when the second truck arrives.

If something goes wrong

The request is confirmed: is the fuel in the tank?

No. Confirmation creates a pending delivery. Stock only changes when the actual delivery is recorded.

“Another manager must approve this request”

You created this request. Ask another station manager, a regional manager or the owner. If you are the only approver for the station, FuelOps lets you decide and records it.

How do I cancel an order?

On the order, click “Cancel order” and give a reason. Deliveries already recorded are kept. If a supplier invoice is linked, void it first in “Supplier Invoices”.